Case Study

Basement Conversion, Highgate N6

Full basement excavation and conversion beneath a detached Edwardian property in Highgate Village, creating 85 sqm of habitable space including a home cinema, gym and guest suite. 14-month specialist programme with complex underpinning.

Programme14 Months
Budget Band£550k – £720k
Core WorksBasement Excavation + Conversion
Result85 sqm New Living Space

Unlocking 85 sqm Beneath a Highgate Villa

This substantial detached Edwardian property in Highgate Village had no existing basement. The owners wanted to create a full-height habitable basement comprising a home cinema, gym, guest bedroom with en-suite and a utility-plant room.

Our structural engineer designed a full underpinning scheme using a contiguous piled wall system, allowing us to excavate to a clear internal height of 2.7 metres while minimising vibration risk. A Type C cavity drain membrane system with dual sump pumps provides waterproofing.

Natural light was introduced through three pavement-level lightwells, supplemented by circadian-tuned LEDs. A dedicated MVHR unit serves the basement level, maintaining fresh air and humidity control independently.

The cinema room features acoustic isolation with independent stud walls, a floating floor and acoustic ceiling tiles, creating a genuinely immersive environment with zero sound transfer to the rooms above.

Project Timeline

1
Weeks 1–4

Site Investigation

Comprehensive ground investigation including boreholes and groundwater monitoring. Structural survey of existing foundations. Tree root protection assessment.

Borehole investigation Groundwater monitoring Tree root protection assessment
2
Weeks 5–10

Structural Design

Contiguous piled wall scheme designed. Underpinning sequence planned. Waterproofing strategy specified.

Piled wall design Underpinning sequence plan Waterproofing specification
3
Weeks 11–16

Planning & Approvals

Planning application with Construction Management Plan. Building control application. Condition surveys of neighbouring properties.

Planning & CMP approval Building control application Neighbour condition surveys
4
Months 5–8

Piling & Excavation

Mini-piling rig installed. 32 CFA piles installed. Bulk excavation followed by reinforced concrete floor slab.

CFA piling (32 piles) Bulk excavation RC floor slab pour
5
Months 9–11

Waterproofing & Services

Cavity drain membrane installed. Dual sump pump system with battery backup. First-fix M&E including MVHR and cinema pre-wire.

Cavity drain membrane Dual sump pump system Basement MVHR installation
6
Months 12–13

Fit-Out

Acoustic isolation for cinema room. Gym fit-out. Guest suite with en-suite. Ground floor reinstated.

Cinema acoustic isolation Gym & guest suite fit-out Ground floor reinstatement
7
Month 14

Commissioning & Handover

Cinema AV system commissioning, MVHR balancing, sump pump testing and snagging. 10-year waterproofing guarantee.

AV commissioning Sump pump testing 10-year waterproofing guarantee

What We Delivered

Full Basement Excavation

New-build basement beneath existing footprint: 85 sqm at 2.7m clear height using contiguous piled walls and sequential underpinning.

Home Cinema Room

Acoustically isolated cinema with 4K projector, 7.2.4 Dolby Atmos and tiered seating for eight.

Gym & Guest Suite

Fully equipped gym with rubber flooring and dedicated ventilation. Adjacent guest bedroom with en-suite.

Waterproofing & M&E

Type C cavity drain with dual sump pumps, battery backup and remote monitoring. Dedicated MVHR and underfloor heating.

Investment Breakdown

How the project budget was allocated across the major work packages.

Piling, Excavation & Structure~48%
Waterproofing & Drainage~14%
Fit-Out, Cinema & M&E~28%
Professional Fees & Contingency~10%

Problems We Solved

Challenge

Ground Conditions

High clay content soil with seasonal movement, plus a mature oak tree within the zone of influence.

Solution

Piled wall solution designed for clay heave. Tree protection plan agreed. Root barrier installed along excavation perimeter.

Challenge

Zero Structural Damage

Excavating beneath a 120-year-old structure while maintaining the occupied upper floors throughout.

Solution

Phased underpinning with monitoring stations on each corner. Real-time movement data reviewed daily. 5mm tolerance never exceeded.

The basement has genuinely transformed how we use our home. The cinema room is the envy of every visitor, and having a proper gym downstairs means we actually use it. The whole process was remarkably well managed.
David & Claire H. Homeowners, Highgate N6