Test the ground, the trees and next door’s footings before a basement is drawn.

Discuss your project

Converting a cellar or excavating a new basement

What lies beneath the ground floor today shapes the whole route. The Planning Portal’s basement planning page treats turning an existing basement into living space as unlikely to need permission, then lists the exceptions: forming a separate home, a significant change of use such as running a business from it, adding a lightwell, or altering how the outside looks. Digging a basement where none exists, or enlarging one, is likely to need permission because of the scale of the works, and a lightwell at the front, visible from the road, may face stricter scrutiny than one at the side or back. The page also warns that councils can set their own limits on how deep and how large a basement may go.

The 2009 Emerson Park Policy Area document contains no clause written for basements. What it does say still reaches underground: its tests cover the landscape features that give the area its character and the space between buildings, and it bars the conversion of houses into flats in every sector, which tells against planning a new lower floor as a self-contained flat. Lightwells, external stairs, vents and plant all show above ground, so we take an outline proposal to Havering’s planners for an early view on the specific address before the structure is designed.

Ground, groundwater and drainage checks

A postcode says nothing reliable about soil or water, so ground investigation comes before design. Our first screen is the government’s long-term flood risk check, which reports an area’s exposure to flooding from rivers and the sea, from surface water and from reservoirs, and from groundwater wherever data is held. That is a desk result, not a site finding. It is followed by trial pits or boreholes to identify the soil and to see whether water collects at the depth of the proposed slab, and by a camera survey of the existing drains, which may cross the area to be dug.

Those results drive the construction choices: how the retaining walls and slab are engineered, which waterproofing system is used and whether pumped drainage with a sump is needed, and how the sides of the dig are supported while open. Daylight, ventilation and a safe way out of the new rooms are designed at the same time, together with the route for services into the lower floor. Building control is a separate approval from planning; Havering lists a full plans application as the most detailed of its routes, meant for larger and more complex projects, and on a basement we favour it so that the structural and waterproofing details are checked before excavation begins.

Mature trees and the planted gardens

Big, planted gardens are part of what the Policy Area protects, and they are where basement work most often meets roots. The 2009 document refuses development that would significantly reduce the landscape features contributing to Emerson Park’s character and expects generous planting in every scheme, while the Havering Local Plan, in Policy 27, wants to know how existing features will be safeguarded during building work. Havering’s tree preservation guidance requires the council’s consent before anyone works on a protected tree, points owners to its online map to check protection, and warns that unauthorised work can end in prosecution.

So before the basement footprint is settled, an arboriculturist surveys the trees near the house and the root protection areas go onto our drawings. Excavation, piling equipment, spoil heaps and conveyors are then kept out of those areas, or the design moves, rather than relying on consent arriving later. The same survey logs the hedges and shrubs along the boundaries, because replanting once the work is finished forms part of the generous landscaping the 2009 rules expect.

Structure, underpinning and notice to neighbours

Digging beneath a lived-in house is structural work from the first day. Our in-house structural engineers begin with a survey of its foundations, walls and floors, open trial holes beside the footings to see what they rest on, and design the retaining walls, the new slab and any underpinning together with the temporary props that carry the house while the ground beneath it is open. The order of digging is fixed on those drawings, not improvised on site.

Neighbours come into it early. GOV.UK’s list of notifiable work covers excavation near a neighbour’s building that goes deeper than its foundations and, on a shared wall, cutting into it or taking it deeper, which is what underpinning a party wall amounts to. Havering’s 2011 extensions guide describes the Party Wall Act as a framework for preventing and resolving disputes over party walls, boundary walls and excavations near neighbouring buildings. In the semi-detached houses of Sector 5 the shared wall is the first question; for a detached house, a dig that stays inside the plot can still reach close enough to next door’s foundations to need notice.

Moving spoil off residential roads

Excavated soil is the bulkiest thing a basement produces, and every load leaves by road. Under Havering’s rules on skips and building materials, nothing may sit on the highway without a written licence; a skip or a materials pile on the road has to carry signs, be guarded and be lit once it is dark, and skip licences are obtained through the hire company. Bay suspensions are reserved for utility and street-works companies, so builders are pointed instead to the council’s parking dispensation arrangements. If part of a front garden becomes the working area, we protect what can remain and replant afterwards, since Havering’s 2011 guide expects front gardens to keep an element of soft landscaping.

Breaking out and digging are the loudest stages. Havering’s nuisance information pack suggests reasonable hours for continuing building work of 8am to 6pm, Monday to Friday, and 8am to 1pm on Saturday; the pack presents these as advice, not a statutory limit, and we keep the noisiest tasks within them. Before excavation starts, neighbours receive a note naming a site contact and explaining when spoil collections and deliveries are expected, and we talk through with the household whether to move out while the house is propped.

Continue planning

Start with the Emerson Park area guide for the sector map and the approvals that may apply, then our basement conversion page for London for the wider sequence. Hampstead Architecture & Planning coordinates the design, and Hampstead Chartered Surveyors & Building Consultancy can carry out the structural and party wall surveys a basement calls for.

Discuss your project

Tell us what you are planning in Emerson Park

Share the property location, the work you have in mind and any drawings or permissions you already have.

£5M public liability, £10M employers' liability and contractors' all risks cover.

Design support: Hampstead Architecture & Planning. Surveying support: Hampstead Chartered Surveyors & Building Consultancy.

Your details will be used to respond to your enquiry. Read our privacy policy.