Insight · 6 min read

Office Furniture Procurement: Fit-Out Budget Integration

Furniture is 10–25% of a commercial fit-out budget but sits outside most main contractor scopes. This guide explains specification, procurement routes, how to integrate furniture with the fit-out programme, and who decides what furniture sits in CAT A+ vs CAT B.

Published 2026-04-15Hampstead Renovations Commercial

The furniture budget share

Commercial furniture typically represents:

For a 10,000 sqft CAT B at £180/sqft (£1.8M), furniture budget typically £180k–£360k.

Furniture scope — what's included

Standard commercial office furniture scope:

Procurement routes

  1. Through main contractor (turnkey)

    Contractor procures all furniture on cost-plus basis. Simplest for client. 8–12% markup typical. Single point of contact.

  2. Specialist furniture dealer

    Separate contract with furniture dealer (Steelcase, Herman Miller, Knoll, Orangebox distributors). Direct client relationship, direct discounts. Client manages two contracts.

  3. Architect / designer specification + tender

    Architect specs furniture; client tenders separately. Best design control. Additional consultant fees.

Lead times and programme integration

Furniture lead times can extend a fit-out programme:

Order furniture at Stage 3 design freeze (typically 10–12 weeks before PC). Any later risks PC delay.

CAT A+ vs CAT B dividing line

In CAT A+ spaces, the landlord includes basic furniture — workstations, task chairs, meeting-room tables, reception seating. CAT B furniture is bespoke to the occupier: brand-matched lobby pieces, executive office furniture, boardroom commissions.

Landlord CAT A+ furniture spec is typically mid-market (Herman Miller Aeron level or OEM equivalent). Occupiers wanting premium tend to accept the landlord contribution as a credit and procure upgrade separately.

Common procurement issues

  1. Late decision

    Client finalises choice at PC-6 weeks. Lead time now runs past PC. Options: pay rush premium (20–40%), accept stock alternatives, or delay PC.

  2. Wrong floor loading

    Dense filing or equipment exceeds base-build floor capacity. Requires structural review or redistribution.

  3. Access / lift sizing

    Large boardroom tables don't fit in building lifts. Require disassembly or crane delivery.

  4. Delivery window conflict

    Furniture arrives same day as final cleaning. Neither process happens well.

Acoustic and ergonomic standards

What we do

Furniture available as cost-plus turnkey with the main fit-out contract, or as specification-only where client procures direct. Bespoke joinery (reception desks, boardroom tables) delivered in-house or with Kelly Hoppen/Walpole-accredited partners. See Office Fit-Out, Reception Refurbishment.

FAQs

Can we install furniture post-PC?

Yes — many fit-outs sign off PC and install furniture during the following 1–2 weeks. Clear temporary arrangements with the landlord for move-in hours.

Who takes delivery risk on furniture?

Depends on contract: turnkey = contractor; direct = client. Direct procurement avoids contractor markup but concentrates risk.

Are second-hand commercial furniture options viable?

Yes — used office furniture market (via brands like Rype Office) can cut budget 30–50% on workstations and task chairs. Trophy spaces typically specify new.

Need commercial expertise on this?

Measured survey and fixed-price quote within 10 working days.