Single floor 8-14 weeks; multi-floor 12-22 weeks; full building 6-12 months. Here's how the typical office refurbishment programme breaks down.
Homeowners comparing scope, planning, finish level, and delivery fit before they ask for quotes.
Hidden enabling works, services renewal, structural complexity, access constraints, and finish ambition.
Use the guide to narrow the right project route before moving into exact service and area pages.
Built to support real renovation, refurbishment, and planning decisions rather than generic blog filler.
Connected to owner-area and exact local service routes where stronger commercial intent lives.
Secondary terms are used to broaden coverage without splitting intent across thin keyword pages.
Structured around local property, planning, cost, and route-ownership context to make the article practically useful.
What this guide covers
Google wants useful pages, not long pages for the sake of it. These section links make the topic structure clearer for readers and keep the article focused on the practical decisions behind the query.
Single-floor refurbishment programme
A typical single-floor office refurbishment in London runs 8-14 weeks on site, with 4-8 weeks of pre-mobilisation. The on-site programme typically splits: site protection and strip-out (week 1-2), structural and first-fix services (week 2-5), plastering and insulation (week 5-7), second-fix services and joinery (week 7-10), kitchens, bathrooms, finishes (week 10-12), snagging and handover (week 12-14). Pre-mobilisation covers design, scope confirmation, fixed-price quote, contract, and landlord approvals. Most landlord licences-to-alter take 3-6 weeks.
Multi-floor and whole-building programmes
Multi-floor refurbishments add 4-8 weeks per additional floor with phased delivery. Phasing typically allows tenant occupation of completed floors while works continue elsewhere — common when the client wants to remain operational throughout. Whole-building refurbishments (10+ floors) typically run 6-12 months with phased handover. Critical-path items: structural alterations, lift refurbishment if in scope, façade works, and main service replacements. Trophy buildings often add 4-8 weeks to programme due to permit and sign-off complexity.
Where programmes typically slip
Most overruns happen at one of three points. First, landlord approvals taking longer than the 3-6 week assumption — particularly in trophy buildings where managing-agent permit portals can have backlogs. Second, asbestos or other surprise discoveries during strip-out — a refurbishment and demolition (R&D) survey before mobilisation reduces this risk. Third, specification changes mid-programme — locking specification at design freeze, before contract, prevents the most common cost-and-time overruns. Variations during delivery are 3-5x more expensive than the same work specified upfront.
How to compress a programme safely
Two common compression methods: (1) overlap design and procurement with mobilisation — start procurement of long-lead items (steels, glazing, kitchens) at design freeze rather than waiting until contract; (2) extended working hours — adding Saturday and evening shifts can compress programme by 20-30% but adds 25-40% to labour cost. Avoid: skipping snagging or handover phases. Defects discovered post-handover cost 5-10x more to fix than during snagging, plus disrupt the client.
Frequently Asked Questions
Can you compress a 14-week programme into 8 weeks?
Sometimes — extended working hours and overlapping procurement can compress 20-30%. Beyond that, programme risk rises sharply and quality usually suffers.
What's the longest single-floor programme you've done?
A trophy floor with bespoke joinery and complex M&E modifications ran 22 weeks. Variations and design changes added 4 weeks vs original 18-week programme.
How early should we start the design phase?
12-16 weeks before target site mobilisation. This allows design freeze, fixed-price quote, contract, and landlord approvals in parallel.